Forever Upgrading

Article by Stephen Groves

Written by Stephen Groves

12 March 2019

Forever Upgrading

Our new melting furnace has been installed 🔥

Due to the continuing rapid business growth at ECO-Masterment, in order to cope with the increase of material being melted, to speed up the throughput, there was a need to substantially increase the melting capacity. After much deliberation, it was decided that the existing furnace would be replaced by a new induction furnace with 8x capacity.

The hugely successful project took 6 weeks to complete and with the addition of a new cooling tower, greatly improved extraction and a bar mould turntable, a week’s melting is now done in a day.

Environmentally, the new equipment is far more efficient even when melting small lots.

More on ECO Mastermelt: www.eco-mastermelt.com.sg


Posted on by Stephen Groves Article Details

Title – Forever Upgrading

Companies – ECO-Mastermelt, Group News

Want to know more? Please contact us.